PK0-004: Introduction to CompTIA Project+ Exam
The CompTIA PK0-004 Exam is challenging and thorough
preparation is essential for success. This exam study guide is designed to help
you prepare for the Project+ certification exam. It contains a detailed list of
the topics covered on the Professional exam, as well as a detailed list of
preparation resources. This study guide for the CompTIA Project+ will help
guide you through the study process for your certification.
PK0-004 CompTIA Project+ Exam Summary
● Exam Name: CompTIA Project+
● Exam Code: PK0-004
● Exam Price: $358 (USD)
● Duration: 90 mins
● Number of Questions: 95
● Passing Score: 710 / 900
● Reference Books: Click Here
●
Schedule Exam: CompTIA
Marketplace
● Sample Questions: CompTIA Project+ Sample Questions
● Recommended Practice: CompTIA
PK0-004 Certification Practice Exam
Exam Syllabus: PK0-004 CompTIA Project+
1. Project Basics- 36%
● Summarize the properties of a
project.
● Classify project roles and
responsibilities.
● Compare and contrast standard
project phases.
● Identify the basics of
project cost control.
● Identify common project team
organizational structures.
● Given a scenario, execute and
develop project schedules.
● Identify the basic aspects of
the Agile methodology.
● Explain the importance of human resource, physical resource, and personnel management.
2. Project Constraints- 17%
● Given a scenario, predict the
impact of various constraint variables and influences throughout the project.
● Explain the importance of risk strategies and activities.
3. Communication & Change
Management- 26%
● Given a scenario, use the
appropriate communication method.
● Compare and contrast factors
influencing communication methods.
● Explain common communication
triggers and determine the target audience and rationale.
● Given a scenario, use the
following change control process within the context of a project.
● Recognize types of organizational change.
4. Project Tools & Documentation-
21%
● Compare and contrast various
project management tools.
● Given a scenario, analyze
project centric documentation.
● Identify common partner or
vendor-centric documents and their purpose.
CompTIA PK0-004 Certification Sample Questions and
Answers
To make you familiar with CompTIA Project+ (PK0-004) certification exam structure, we have prepared this sample question set. We suggest you try our Sample Questions for Project Plus PK0-004 Certification to test your understanding of CompTIA PK0-004 process with the real CompTIA certification exam environment.
PK0-004 CompTIA Project+ Sample Questions:-
01. In
which of the following team development stages would the project manager MOST
likely determine the structure of the project team?
a) Storming
b) Norming
c) Forming
d) Performing
02.
Which of the following are risk responses?
(Choose two)
a) Delaying
b) Analysis
c) Acceptance
d) Avoidance
e) Work around
03.
While developing a project schedule, which of the following are purposes of a
milestone?
(Choose two)
a) Milestones are not required since the major
events are already placed in the project work plan without durations
b) Milestones are considered a placeholder in
time for a major event
c) Milestones have no duration
d) Milestones are indicators that any of the
project major events have already taken place
e) Milestones require a duration indication as to provide the key stakeholders of information as a key performance indicator (KPI)
04.
Which of the following is the key characteristic of the WBS?
a) It represents the entire scope of work for
the project
b) assists the project manager with the
qualified vendor selection process
c) It should be developed by others outside
the project team as to eliminate bias
d) Eighty percent of the work packages will be developed by twenty percent of the project team
05.
Which of the following tools is used for determining activity schedules based
on optimistic, most likely and pessimistic estimates?
a) Key event/activity list
b) PERT
c) CPM
d) Gantt
06.
When handling multiple changes on a project, which of the following would be
the BEST format in which to inform the team?
a) Follow the communication plan
b) Email documentation
c) Fax documentation
d) Hold a meeting with the project team
07.
Which of the following network diagram methods uses arrows to represent
activities, but is limited because it can only represent Finish-to-Start
dependencies?
a) Arrow Diagramming Method (ADM)
b) Work Breakdown Structure (WBS)
c) Precedence Diagramming Method (PDM)
d) Critical Path Method (CPM)
08.
Which of the following is the condition in which the team just cannot finish
the last piece of work and cannot complete the project?
a) The 80/20 rule
b) The progressive elaboration
c) The 95 percent phenomenon
d) The law of diminishing returns
09.
Which of the following would be important to remember when scheduling a
teleconference for a project team?
a) Providing food for the meeting to keep
members satisfied
b) Identify morning or afternoon personalities
of team members
c) Securing a meeting room that has sufficient
seating
d) Considering time zone that meets business hours for whole team
10.
Which of the following is a formula for estimating?
a) (BAC-EV)/CPI
b) Actual Cost + Estimated Time to Completion
c) EV/PV
d) (Optimistic + (4 x Most Likely) +
Pessimistic) / 6
Answers:-
Question:
01:- c
Question:
02:- c, d
Question:
03:- b, c
Question:
04:- a
Question:
05:- b
Question:
06:- a
Question:
07:- a
Question:
08:- c
Question:
09:- d
Question: 10:- d
Comments